Permitting is where most fire rebuilds lose the most time — and where preparation helps most. Here is what Spokane County reviews, what gets easier when you rebuild the same footprint, and how to keep your submittal out of the correction cycle.
Of the 14 to 24 months a fire rebuild takes, a surprising share is spent waiting for paper. Permitting is also the phase homeowners have the most influence over — not by pushing the county, but by submitting a complete, correct application the first time.
Here is how the process works in Spokane County and the City of Spokane, and where rebuilds get stuck.
Requirements change and this is general guidance. Confirm current requirements with Spokane County Building and Planning or the City of Spokane Development Services Center before you submit — and if you are outside those jurisdictions, with your own city.
First: which jurisdiction are you in?
This matters more than people expect. Spokane County Building and Planning handles unincorporated areas — where most of the Spokane Complex burn area sits. The City of Spokane, City of Spokane Valley, Liberty Lake, Medical Lake, Airway Heights and Cheney each run their own permitting.
Fee schedules, review timelines, submittal checklists, and inspection scheduling all differ. Confirm your jurisdiction from your parcel number before you spend a dollar on drawings.
The good news about rebuilding on an existing footprint
A rebuild is not a new subdivision lot. When you rebuild the same structure in the same place, a lot of the hardest entitlement questions are already answered:
- Setbacks are already established and were legal when built
- Septic siting and drainfield location already exist and are on record
- Driveway approach and access are already permitted
- Water service or well is already in place
- Non-conforming conditions — a house closer to a property line than current code allows — can frequently be rebuilt as they were, provided you stay within the original footprint
That last point is worth real money. Change the footprint and you may lose a legal non-conforming status you cannot get back.
This does not mean you rebuild to the old code. The structure is built to the current adopted code. It means the land-use questions are largely settled.
What a residential rebuild submittal includes
Expect to provide most of the following:
- Completed application with parcel number, legal description, and owner information
- Site plan — property lines, setbacks, the structure footprint, driveway, well and septic locations, easements, and topography
- Architectural drawings — floor plans, elevations, building sections, and construction details, dimensioned and to scale
- Structural engineering — foundation design, framing plans, lateral bracing, and connection details, stamped by a Washington-licensed engineer where required
- Washington State Energy Code compliance forms — envelope values, the energy credit worksheet, and equipment efficiencies
- Septic approval from the Spokane Regional Health District if you are on an on-site system — often required as a prerequisite to building permit issuance
- Well documentation where applicable
- Driveway or approach permit, if access is changing
- Stormwater and erosion control for larger disturbed areas
- Wildland-urban interface documentation where applicable — exterior assembly specifications and defensible space
Typical residential review runs 4 to 10 weeks in normal conditions. After a mass-loss event, queues lengthen — though jurisdictions commonly stand up expedited rebuild tracks, fee waivers or reductions, and dedicated recovery staff. Ask specifically whether a disaster-rebuild track exists. It often is not advertised prominently.
Where submittals get stuck
Nearly every correction cycle we see comes from the same short list:
- Incomplete energy code documentation. The Washington State Energy Code credit worksheet is exacting, and it is the single most common correction on residential submittals.
- Missing septic approval. The health district review runs on its own schedule. If your building permit is waiting on it, you have lost weeks you did not need to lose. Start it in parallel, early.
- Site plan that does not match the survey. Setback dimensions that do not tie to actual property corners.
- Unstamped structural details where the span, height, or seismic/wind category requires an engineer.
- Undocumented WUI compliance. If your parcel is in a designated wildland-urban interface area, the exterior assemblies have to be specified on the drawings, not decided in the field.
Every one of these is preventable at submittal.
Sequencing that saves months
Run these in parallel rather than in series:
- Design starts during debris removal. Nothing about drawing a floor plan requires a clear lot.
- Septic evaluation starts with design, not after permit submittal.
- Structural engineering runs alongside architectural drawings, not after them.
- Foundation evaluation — if any of the original foundation might be reused — happens early, because the answer changes the drawings.
The families who finish first are almost always the ones who compressed the front end, not the ones who pushed the construction schedule.
Inspections
Once permitted, expect roughly this sequence, each requiring a passed inspection before the next phase proceeds:
- Footing / setback
- Foundation and damp-proofing
- Underground plumbing and electrical
- Framing, plus separate plumbing, mechanical and electrical rough-ins
- Insulation and air sealing, including the blower-door test
- Drywall / gypsum nailing
- Final building, plumbing, mechanical and electrical
- Certificate of Occupancy
Inspection scheduling is a real schedule variable. Local builders know how far ahead to call, which combinations get scheduled together, and what each inspector wants staged and ready. It is one of the least glamorous and most valuable things an established local contractor brings.
Fees, and what may be waived
Building permit fees in Spokane County are generally calculated from valuation, with plan review as a percentage on top, plus separate mechanical, plumbing and electrical permits and any applicable impact fees.
After a declared disaster, jurisdictions frequently waive or substantially reduce rebuild permit fees for the destroyed structures. Ask directly. It is rarely applied automatically.
Also note: permit fees, plan review, and design costs are legitimately part of a rebuild claim. Itemize them.
Who pulls the permit
The contractor should. When a homeowner pulls an owner-builder permit, the homeowner assumes responsibility for code compliance, inspections, and — under Washington rules — potentially for the conduct of everyone working on site. There are narrow situations where it makes sense. A post-fire rebuild is not one of them.
Verify any contractor's registration through the Washington State Department of Labor & Industries "Verify a Contractor" tool before signing anything: active registration, bond, liability insurance, and complaint history.
We do this part for you
We have been pulling permits in Spokane County since 1967. We know the submittal checklists, the correction patterns, the health district timelines, and the inspectors. For a family that just lost a house, having someone else absorb this phase is not a luxury.
If you are rebuilding and want the permitting handled properly, reach out. And if you are earlier in the process, start with our step-by-step rebuild guide.